Review new standards to understand changesRemove multibeam system for repairs and if not back in time for survey, hire a replacementCheck survey staff availability for new datesCancel multibeam part of workHire a contractorUse a different vessel
Escalated to the vessel operations manager to discuss potential options
Project manager negotiated with equipment repair company to ensure that the broken equipment would be available on time. Hire equipment was also put on reserve
Vessel operations manager reviews new survey standard specifications
Project manager asks Team leader to check with survey team if they are available for different dates for the survey
Minimal changes to survey standards requires no extra work before survey2 members of staff aren't available for survey, so 1 reserve with the same skill level join the team and 1 contractor hiredThe equipment is repaired and returned before the start of survey, excess cost is not charged to the main budget, but goes to vessel reserves