  • Eh, tadi ada request untuk erect scaffold kat vibration line urea tu.... dah erect?
  • Requestor
  • GSRF form baru saya receive tadi, then PR sudah create. Nanti MAC akan approve the PR.
  • Lead Planner GS
  • Oh, kena approve dulu ker. tak boleh buat terus? Urgent nih
  • Kena follow work process la, kalau PR belum approve, then belum boleh issue RO to contractor. Nanti ada issue Retro, serious tau...
  • Requestor
  • Lead Planner GS
  • Oh, baru I faham the impact, this may cause Retro. ok, nanti i follow-up with MWC.
  • P1/P2 pun kena follow, but we will expedite and put priority for the job. You boleh tanya MWC nanti on the update at site.
  • Requestor
  • Lead Planner GS